Task
-
Resolution: Done
-
Low
-
None
As per the release process 5 weeks prior we need to create a fresh installation of the QA testing site.
- Disable hourly and daily syncs
- Backup current qamaster
- Delete qamaster and recreate using the most recent backup
- Upgrade qamaster to latest 3.11dev
- Add or change data on the site as required
- Re-enable the sync scripts
- Create a backup of qamaster
Notes:
- At 12:00 UTC qamaster auto-upgrades to the latest dev version from git://git.moodle.org/integration.git
- At 13:00 UTC qa is updated to match qamaster and any changes made to qamaster will be available on qa
- A new backup of qamaster should be requested at any time after substantial changes have been made to the site e.g. at the end of the QA cycle.
- has a non-specific relationship to
-
MDLSITE-6593 Get QA testing site ready for the 4.0 QA cycle
-
- Closed
-
- has been marked as being related by
-
MDLSITE-6847 Get QA testing site ready for the 4.1 QA cycle
-
- Resolved
-
-
MDLSITE-6237 Get QA testing site ready for the 3.10 QA cycle
-
- Closed
-