Prepare a fresh installation of the QA site based on the beta code to make sure the site is not affected by incremental upgrade steps during the development cycle.
Procedure:
- Disable both the hourly and daily syncs
- Set up qamaster directly
- Reassign issue to marycooch to add courses and other content
- Mary to reassign issue when done, then both sync scripts can be re-enabled
- is a clone of
-
MDLSITE-3418 Create a fresh install of the QA testing site
-
- Closed
-
- Testing discovered
-
MDLSITE-2974 QA testing site missing countdown timer
-